What is the Peatland Code?
Watch our introductionary video of the  Peatland Code v2.1 to find out.


If you have decided to undertake a peatland restoration project and would like to become Peatland Code validated, and later verified, the following steps outline the process.

PC timeline 2025

Step 1 - Establish eligibility 

Download the Peatland Code and establish if your project is eligible.  

For a project to be eligible for validation/verification to the Peatland Code (at present) the following basic pre-requisites must be met:


•    Peat soils must be greater than 30cm in depth for bogs with additional requirements, 45cm in fens
•    Peatland type must be blanket, raised bog or fen
•    Peatland condition must be 'Actively Eroding', 'Drained', ‘Modified bog’, ‘Cropland – drained’, ‘Grassland - intensive’  'Grassland - extensive’ or ‘Modified fen’ (See Field Protocol for definitions)
•    Restoration activities must not include forestry removal
•    Restoration must not be legally or contractually required
•    Project must be able to enter a minimum contract of 30 years
•    Restoration activities must not conflict with any other land management agreements
•    Project must be additional i.e. it must require carbon finance to take place

These eligibility requirements are to be used as a quick indication of eligibility only. Full details can be found within the Peatland Code. 

Before embarking on the following steps projects may wish to consult a Project Developer. Please note Project Developers provide a paid service and will charge a fee. 

Step 2 - Register the project on the UK land carbon registry

If working with a Project Developer they will register the project. 

Create a IHS Markit, now a part of S&P Global, account and register the relevant project (please see the User Guide). You can also search the public register

For more information on the Registry and associated fees please see the Peatland Code Registry section of this site.


Step 3 - Complete Peatland Code documentation

Complete a field survey of the project site and complete the required Peatland Code documentation (see below)

To demonstrate compliance with the requirements of the Peatland Code a number of actions and forms must be completed. The documents, available to download below, provide all the information required to carry out this step:

For all projects see Peatland Code Guidance, Clarification Document and Field Protocol. 

Fens 

 

 

Bogs

Extension Requests

During the Peatland Code Project Plan/Restoration Validation or Verification process you may apply for an extension. Requests are submitted via the Extension Request Form and are not guaranteed for approval, they are considered on a case by case basis. Please apply with as much advance notice as possible.

Step 4 - Project Plan validation

Contact an appointed validation body to carry out your project validation. This is a paid service, for quotes please contact the validation bodies directly.

The current bodies approved to validate and verify Peatland Code projects are OF&G, and Soil Association for more information on our Validation and Verification bodies (VVB) see here. Project Plan Validation and Restoration Validation must happen to the same Pealtand Code version. To check which version your project can validate agaisnt see our Peatland Code version history document. 

Once projects have appointed a VVB,  the VVB will arrange a date to carryout an audit of both the project site and the project documentation. Amendments to the project plan may be required if determined necessary by the validation/verification body to ensure compliance with the Peatland Code. 

The validator submits directly to the Peatland Code team all the documents required for a validation review. At this stage, the validator has already performed their checks and had detailed contact with the Project Developer. The validator sending through the documents is confirmation that they believe the project should be validated to the Peatland Code. Full details on VVB requirements are outlined in our VVB Scheme Document V1.0.

Step 5 - Peatland restoration

Secure funding and start/complete restoration activity as per Project Design Document. 

A public register of all available Peatland Code projects is available online, allowing potential buyers to search for one that meets their requirements. Alternatively, projects can use the services of a specialist carbon broker to actively search for a buyer on their behalf. A sale can also result from a direct relationship, for example between a land manager/owner and a local business. Projects can sell the climate benefits at any time. By marketing the additional benefits that arise alongside the climate benefits of peatland restoration it may be possible to achieve a greater purchase value. 

Step 6 - Restoration validation

Within one year of finishing the restoration activities detailed in the Project Design Document the Project must arrange an independent Validation/Verification body to assess the restoration work on site. This validation of the restoration activity will check if the project has delivered the planned restoration work to a good standard and adjust the expected emission reductions if necessary. A ‘Restoration Validation’ certificate is awarded stating the amount of expected emission reductions and the corresponding number of Pending Issuance Units (PIUs). If Pending Issuance Units were issued before restoration commenced these can be adjusted according to the Restoration Validation certificate. 

 

Step 7 - Verification

Following successful validation and completion of the restoration activity a regular schedule of verification audits will be conducted by the validation/verification body. This will ensure the project achieves and maintains the expected condition category change, delivering the expected greenhouse gas benefit over its duration.

The project must submit the following documents to the verification body.

Project Progress Report 

Year 5- Verifcation Emissions Calculator (15% buffer contribution)

Year 5 - Verification Emission Calulator ( 20% buffer contribution)

 

Peatland Code Grievances:

The IUCN UK PP is committed to ensure that the grievance and appeal process is as transparent and fair as possible. If you have any of the grievances related to the application of the Peatland Code please complete this form with as much information as possible and email it to the info@iucn.org.uk and copy in the peatlandcode@iucn.org.uk. Our disputes coordinator will then confirm receipt of your grievance within 15 working days and assign you a unique reference number. More information on our appeals and grievance process can be found here.

 

Peatland Code logo

Neolithic trackway on Hatfield Moors. Credit: Henry Chapman Uni of Birmingham
New publication: Tracks and roads on peatlandsThe IUCN UK Peatland Programme are pleased to publish our latest brief focusing on the impacts of…
Peatland landscape showing flux tower and solar panel with a blue sky and hills in the background. Image credit Hollie Cooper, UKCEH
Funding announced for greenhouse gas reduction solutions on peatlandsThe UK Centre for Ecology and Hydrology is seeking proposals for projects up to £75,000 to advance…
Hare's tail cottongrass on Humberhead levels
Committee on Climate Change (CCC) 7th Carbon Budget Report - a response from IUCN UK Peatland ProgrammeThe IUCN UK Peatland Programme welcomes this week the publication of the Committee on Climate…
Water vole sitting with blackberries
New species showcase - Water voleContinuing the spotlight on peatland biodiversity, our first Species Showcase of 2025 is the Water…
Digger being used to carry out peat bog restoration. Photo: Montgomeryshire Wildlife Trust
Adoption of University of Cumbria PhD student’s carbon calculator brings national and international significanceThis week University of Cumbria and Barker and Bland Ltd.’s innovative carbon calculator has been…
Image advertising launch of the CivTech Round 10 Challenge
CiVTech innovators leading drive for advances within Peatland and Woodland Carbon CodesBringing efficiences to the Peatland Code and Woodland Carbon Code is the focus for three…
Interior of the Virtual Peatlands Pavilion, showing the information desk with a giant dragonfly and globe suspended above it.
Embark on a voyage of discovery with the Virtual Peatlands Pavilion 2025 world tour To raise awareness of the global distribution and importance of peatlands, the Virtual Peatlands…
Image of a computer screen displaying a survey
Public Consultation for Biodiversity Quantification MethodologyThe Woodland Carbon Code and Peatland Code are pleased to announce their public consultation…
Image of machinery being used on a peatland to restore the habitat
Natural Resources Wales announces new funding for peatland restorationA new restoration fund, managed by Natural Resources Wales (NRW), was launched this week in an…
The IUCN UK Peatland Programme team at the base of Kinder Scout
Reflecting on 2024: a busy year for peatlandsAs the year draws to a close, the IUCN UK Peatland Programme looks back on 2024.
Four people in outdoor clothing looking out across a peatland landscape. Image credit: Mark Reed
Help answer the question: Do investors undervalue the social impact of peatland projects in the UK when making investment decisions?Business professionals at the Cambridge Institute for Sustainability Leadership are seeking…
Photograph of Cornwall Sustainability Awards on a table with a screen in the background
Big Win for Cornwall’s Peatlands at Local Sustainability AwardsThe South West Peatland Partnership (SWPP) has been recognised at the 2024 Cornwall Sustainability…