ScottishPower Renewables trial new ‘wave damming’ method: site visit

February 24, 2016

Scottish Natural Heritage (SNH) Peatland ACTION and IUCN UK PP staff visited Black Law wind farm to see ScottishPower Renewables’ new ditch blocking trial.

Black Law WindfarmScottishPower is seeking to develop a new method to deal with blocking drainage channels. An area of open bog (about 40ha in size) with a dense 23km network of drains, installed during the early 1900s, has become a trial site for a new form of peat damming developed by ScottishPower: wave damming. With no shortage of rain in the preceding weeks, brought in with Storms Gertrude and Henry, it was clear that the trial site was effective in holding water!

The main driver for developing this method was the high cost of installing plastic piling or constructing traditional peat dams across such an extensively and densely drained site. ScottishPower’s ecologists also wanted to discourage the preferential flow that can frustratingly develop around the sides of a newly installed peat dam. The ‘wave damming’ method aims to span the whole cross-section of oxidised peat either side of the cut channel and to block all hydrological flow paths: the process of wasting of peat either side of a drain channel is illustrated by Richard Lindsay in a previous IUCN Peatland briefing note on drainage impact.

Dams are installed very close together, at 3-4m spacing across the ditch. The site we looked at had small ditches, 0.8m deep with a similar width across. The dams are made by drawing in three complete buckets of peat and vegetation from either side of the drain and compressing this to form a long, wide dam. All the dams had pools behind them, usually quite deep after restoration, which were a worry for the local grazier. Minimising the amount of bare, exposed peat is a key concern. These dams have the benefit of vegetation being an integral part of the peat which is pulled in, rather than being ‘capped’ with an excavated layer of peat from elsewhere. It is hoped that this will encourage stability within the surface of the dam wall, reducing slumping and improving its longevity.  

Their ecologists have worked closely with their contractors to develop a method that minimises the risk of vegetation being smothered or flipped as the dam is pulled into place. Essentially, all that is required is some dextrous movement of the digger bucket. With a little practice this can be achieved at a rate of around 1 minute 15 seconds per dam, resulting in an impressive and cost effective amount of restoration works achieved per day.

SNH’s Peatland ACTION Officers raised concern that there might be issues with leaking dams in the future as the dam material is formed from three scoops of the digger bucket to form a dam: water might leak through the joins and reduce the dam’s effectiveness. Extensive baseline monitoring has been installed across the trial area. Long term stability and performance under dry conditions are still and unknown. It is encouraging to see innovation, in what is essentially a long-established technique, and we look forward to seeing how this site develops.

Emma Goodyer

IUCN UK PP Programme Manager

Image of a computer screen displaying a survey
Public Consultation for Biodiversity Quantification MethodologyThe Woodland Carbon Code and Peatland Code are pleased to announce their public consultation…
Image of machinery being used on a peatland to restore the habitat
Natural Resources Wales announces new funding for peatland restorationA new restoration fund, managed by Natural Resources Wales (NRW), was launched this week in an…
The IUCN UK Peatland Programme team at the base of Kinder Scout
Reflecting on 2024: a busy year for peatlandsAs the year draws to a close, the IUCN UK Peatland Programme looks back on 2024.
Four people in outdoor clothing looking out across a peatland landscape. Image credit: Mark Reed
Help answer the question: Do investors undervalue the social impact of peatland projects in the UK when making investment decisions?Business professionals at the Cambridge Institute for Sustainability Leadership are seeking…
Photograph of Cornwall Sustainability Awards on a table with a screen in the background
Big Win for Cornwall’s Peatlands at Local Sustainability AwardsThe South West Peatland Partnership (SWPP) has been recognised at the 2024 Cornwall Sustainability…
Aerial image of hagging on a damaged blanket bog landscape. Image credit: Mark Brown
Technical review of remote sensing for UK peatlandsThe IUCN UK Peatland Programme has commissioned a technical review of the potential and…
Salmon leaping out of the water. Image credit Stephen Barlow
New species showcase - Atlantic salmonThe latest in our series of species showcases celebrates the Atlantic salmon and the role that…
Exterior view of Virtual Peatland Pavilion showing four large domes in an urban landscape
New Virtual Peatland Pavilion launched for COP29To raise awareness of the global importance of peatlands during COP29, the latest pavilion has been…
Cover image for 'The most important plant in the world' showing the film's title in yellow text over a background of Sphagnum moss
Specially commissioned film celebrates 'The most important plant in the world'The IUCN UK Peatland Programme has commissioned the first in a series of short films, celebrating…
Cumbrian tarn - large body of water with emergent vegetation and hills in the distance. Image credit Steve Hewert.
Launch of the Peatland Code Version 2.1The IUCN UK Peatland Programme has launched a new update to the Peatland Code, which helps to boost…
Flat peatland landscape on fire with large plumes of smoke. Image credit Paul Turner
New brief highlights the importance of peatland rewetting for wildfire resilienceThe IUCN UK Peatland Programme's latest publication explores recent evidence from the UK and North…
Painting of a river in spate: Peter Graham 1866, 'A spate in the highlands'
Call for proposals for Water Research Seminar SeriesThe IUCN UK Peatland Programme and the Environment Agency are delighted to announce a series of…